|
Pipeline burial along Magzi market road:
|
Work on the Phase I gas distribution network which will deliver gas to and around the Magzi Industrial Estate (total length of approx. 4.5km) commenced on the 15th July 2011. From the Magzi area, which is forecast to receive gas by the end of the year, pi-pipeline operations will continue on to Central Douala. |
|
Ditch Witch ‘pulled pipe’ operation near the Magzi Estate
|
All directional drilling operations have now been completed in the Magzi Industrial Estate Area |
|
Smaller 250mm pipe on the Magzi Industrial Site
|
Smaller diameter pipe (250mm and 63mm), in addition to 400mm pipe, is being buried on the Magzi Estate |
|
Pneumatic pre-test outside our first customer, an iron foundry
|
Today, 99% of the pipeline to the first customer hub, Magzi, is either in the ground or jointed waiting trenching/burial. All buried pipe (approx. 3.5km or 78%) has been back filled and pneumatically tested |
|
Production Facilities (on site)
|
Substantial progress has been made in installation of process plant vessels and pipework on site |
|
Production facilities on site (cont’d)
|
All major equipment and vessels have been landed on their foundations and substantial pipework and manifolds installation is complete. |
|
Wireline operations (running into the hole with logging tools):
|
A wireline (data acquisition) programme on Logbaba La-105 and -106 has been completed. |
|
“My complements to you and your staff regarding the manner in which this Gas Pipeline Installation Project of yours in the Magzi Industrial neighborhood is proceeding. I have a project here myself. We are building a headquarters building and associated plaza and manufacturing plant on the street where your crew is working. |
RDL’s operations have been well received by operators on the Magzi Estate. |